5
Tenders · Enterprise Data Center Migration

Enterprise Data Center Migration

RFP-2034-18 (Round 2)
In evaluationIT — Cloud & Infrastructure·Budget $3M·Closes 25 Apr 2026·Owner: Arjun Sharma

Risk heatmap

Each cell shows the worst-severity flag for that category and vendor. AI surfaced; humans decide.

10 flags · 4 high
Category
ComputeHub
TechNova
NextGen
Cloudify
DataCore
Liability & IndemnityHigh Risk——High Risk—
ValidityHigh Risk——Medium—
Payment Terms———High Risk—
WarrantyMedium————
Local Content—LowMedium——
IP——Medium——
SLA————Medium

Risk register

Each flag links to a source quote with page reference. Resolve, request a clarification, or accept the risk.

  • Liability cap at 2% of contract value

    ComputeHub · Liability & Indemnity · §12.1

    High Risk

    Vendor position

    “Liability shall in no event exceed two percent (2%) of the total contract value.”

    p.35 of 78

    Schema requirement

    RFP §12.1 — Minimum 100% of contract value.
  • Bid validity only 60 days

    ComputeHub · Validity · §4.2

    High Risk

    Vendor position

    “Validity well short of the 120 days requested. Will expire before scheduled award.”

    p.35 of 78

    Schema requirement

    Refer to RFP for the applicable requirement.
  • Liability cap at 5% of contract value

    Cloudify Systems · Liability & Indemnity · §12.1

    High Risk

    Vendor position

    “The total liability of the Service Provider to the Client arising out of or in connection with this Agreement shall not exceed five percent (5%) of the total contract value.”

    p.35 of 78

    Schema requirement

    RFP §12.1 — Minimum 100% of contract value.
  • Advance payment 30%

    Cloudify Systems · Payment Terms · §13

    High Risk

    Vendor position

    “Vendor requests 30% advance; RFP caps advance at 10% with bank guarantee.”

    p.35 of 78

    Schema requirement

    Refer to RFP for the applicable requirement.
  • Warranty period < 12 months

    ComputeHub · Warranty · §14

    Medium

    Vendor position

    “Warranty only 6 months — below the 12-month RFP minimum.”

    p.35 of 78

    Schema requirement

    Refer to RFP for the applicable requirement.
  • Local content below 65% target

    NextGen Infra · Local Content · Annex E

    Medium

    Vendor position

    “Vendor commits 48% in-country resourcing vs RFP target of ≥65%.”

    p.35 of 78

    Schema requirement

    Refer to RFP for the applicable requirement.
  • IP ownership not clearly defined

    NextGen Infra · IP · §16.1

    Medium

    Vendor position

    “IP clauses do not clearly assign ownership of configurations and scripts to client.”

    p.35 of 78

    Schema requirement

    Refer to RFP for the applicable requirement.
  • Bid validity only 90 days

    Cloudify Systems · Validity · §4.2

    Medium

    Vendor position

    “Validity shorter than the 120 days requested in the RFP.”

    p.35 of 78

    Schema requirement

    Refer to RFP for the applicable requirement.
  • SLA penalties not clearly defined

    DataCore Services · SLA · Annex F

    Medium

    Vendor position

    “Service credits referenced but not quantified.”

    p.35 of 78

    Schema requirement

    Refer to RFP for the applicable requirement.
  • Local content marginally below 65% target

    TechNova Solutions · Local Content · Annex E

    Low

    Vendor position

    “Vendor commits 62% in-country resourcing vs RFP target of ≥65%.”

    p.35 of 78

    Schema requirement

    Refer to RFP for the applicable requirement.